Hard1 markMultiple Choice
AZ-305 · Question 47 · Domain 4.3: Migrations
You are planning a large-scale migration of 500 VMware VMs to Azure. You need to discover the on-premises servers, map their network dependencies to group them into migration waves, and get cost estimates for running them in Azure. Which TWO tools should you use? (Select TWO)
You are planning a large-scale migration of 500 VMware VMs to Azure. You need to discover the on-premises servers, map their network dependencies to group them into migration waves, and get cost estimates for running them in Azure. Which TWO tools should you use? (Select TWO)
Answer options:
A.
Azure Migrate: Discovery and assessment.
B.
Azure Site Recovery.
C.
Dependency analysis (agentless or agent-based).
D.
Azure Cost Management.
E.
Data Migration Assistant (DMA).
How to approach this question
Identify the primary Azure migration assessment tool and its dependency mapping feature.
Full Answer
Azure Migrate is the central hub for discovery and assessment. Within Azure Migrate, you use Dependency Analysis to visualize network connections between servers, ensuring you migrate dependent servers together in the same wave.
Common mistakes
Selecting Azure Site Recovery, which is the execution engine, not the assessment tool.
Practice the full Azure Solutions Architect Expert AZ-305 Practice Exam 6
55 questions · hints · full answers · grading
More questions from this exam
Q01Contoso Ltd is a global manufacturing company with 50,000 employees. They operate a mix of on-pre...MediumQ02A financial institution has 500 Windows Server VMs on-premises and 200 VMs in Azure. They need to...HardQ03An enterprise uses Azure Sentinel and Log Analytics. They ingest 500 GB of logs daily. The IT bud...HardQ04You are designing a monitoring strategy for a new Azure deployment consisting of App Service, Azu...EasyQ05A healthcare company uses Microsoft Entra ID (Azure AD). They need to implement a security policy...Medium