    PracticeACCAACCA PM — Performance Management Practice Exam 1Question 11
    Easy2 marksShort Answer
    Quantitative Analysis in Budgeting

    ACCA · Question 11 · Quantitative Analysis in Budgeting

    Section A

    MarineBuild is constructing luxury yachts. The assembly of the yachts follows an 80% learning curve. The time taken to assemble the first yacht was 2,000 hours.

    The learning curve formula is Y = ax^b, where for an 80% curve, b = -0.3219.

    Calculate the total time required to assemble the FIRST TWO yachts. (Enter the number only).

    How to approach this question

    Use the tabular method or formula. For 2 units, the average time per unit is 2,000 * 0.80. Total time is Average Time * 2.

    Full Answer

    Using the doubling rule: As production doubles from 1 to 2 units, the cumulative average time per unit becomes 80% of the time for the first unit. Average time for 2 units = 2,000 hours × 0.80 = 1,600 hours. Total time for 2 units = 1,600 hours × 2 = 3,200 hours.

    Common mistakes

    Calculating the time for the 2nd unit only (3,200 - 2,000 = 1,200) instead of the total time for the first two units.
    Question 10All questionsQuestion 12

    Practice the full ACCA PM — Performance Management Practice Exam 1

    32 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1Section A OmniRetail, a global supermarket chain, is implementing a new Executive Information Sy...EasyQ2Section A CloudTech Solutions, a SaaS provider, is migrating its core financial performance data...MediumQ3Section A ArtisanWood crafts bespoke furniture. The company is adopting Activity-Based Costing (...EasyQ4Section A SiliconForge manufactures semiconductor chips. The factory has a bottleneck process. T...MediumQ5Section A ChemCorp produces industrial solvents. Recently, the company was fined $50,000 by the ...Easy