ACCA · Question 21 · Budgeting
A cloud hosting company prepared a fixed budget for 5,000 server deployments, estimating total costs of $250,000 (comprising $100,000 fixed costs and $150,000 variable costs).
Actual deployments were 6,000.
What should be the total cost allowance in the flexible budget for control purposes?
Answer options:
$250,000
$280,000
$300,000
$330,000