EcoBuild Ltd contracts to construct a sustainable community center for a local NGO, with work to commence on 1 September. On 15 August, EcoBuild informs the NGO that they have taken on a more lucrative project and will definitely not be building the center. What is the legal position of the NGO?
Answer options:
The NGO must wait until 1 September before taking any legal action for breach of contract.
The NGO can treat the contract as discharged immediately and sue for damages, or wait until 1 September to see if EcoBuild performs.
The contract is frustrated due to EcoBuild's inability to perform.
The NGO can only claim an injunction to force EcoBuild to perform the work.